Week 40  This week we get the mud guards.

The bits we received

And what we did with them

The mud guards were fitted, along with the ones supplied last week.  I needed to open out the holes in the sides with a 1.3mm drill.  Then the parts all fitted without any problems.  The middle two parts are identical, and the front and rear parts will only fit one way.  I used super glue for these.  All quick and easy.

Now I can paint the deck.  The outside is all painted dark yellow.

The interior is painted Ivory at the front, and red oxide for the engine compartment.

Things not yet done

Issue 11 : Paint and fit spare track links.
Issue 19 : Fit ball and headlight
Issue 23 : Paint the radiator covers
Issue 24 : Finish the issue
Issue 25 : Complete issue
Issue 32 : Complete the tow cable
Issue 33 : Complete issue
Issue 34 : Paint tools and fit them to the deck
Issue 38 : Paint parts
Issue 40 : Paint the deck

Take me back to week 39

Take me to week 41